Westwood Middle School Transformation Parent Meeting Recap – 5/18

Wolf Image

Thank you to those who attended the first parent meeting regarding the Westwood Middle School transformation project held on Monday, May 18. The following information was shared regarding the upcoming construction and its impact on our campus. Please see the full 5/18 presentation for specifics on each topic as well as the renderings, site plan, and floor plan.

Construction Phasing

The project is divided into phases with the goal of substantial completion by August 2028. Since the new Westwood MS is a new build and will be built on the other side of the existing property, students will continue to attend school in the existing building until its completion for the 2028-29 school year. 

Summer 2026 – Fall 2026

  • Construction fencing and mobilization on site
  • Existing front drive remains opened
  • Temporary Firelane to be complete for school
  • New building under construction

Traffic Management – Fall 2026

  • Two scenarios are being considered for Fall 2026. The final decision will be shared with the community as part of the campus back-to-school communications once construction begins this summer.

Construction Safety

Strict measures are in place to separate students from construction activity:

  • Complete Separation: A complete separation between students/staff and construction workers will be maintained at all times.
  • Personnel: All construction workers must pass background checks and wear badges.
  • Access: Workers will use a separate entrance and park within the construction zone. Only authorized construction staff can unlock gates between the construction and student areas.
  • Coordination: School leadership and the construction team will meet weekly to plan for campus events to minimize impact.

Athletics: Temporary Adjustments for 2026-2027

Due to construction, several athletic facilities will be unavailable on campus, and certain athletics and practices will be moved off-site to nearby sites. Ongoing coordination and communication will take place during the school year. More information will be shared at a future meeting for athletics families 

  • Football @ Spring Creek in 26-27
  • Soccer @ Spring Creek in 26-27
  • Track @ Richardson HS in 26-27
  • Tennis @ Richardson HS in 26-27
  • Volleyball @ Westwood in 26-27
  • Basketball @ Westwood in 26-27

Upcoming Meetings:

  • Athletic Parent Meeting: Early August
  • Parent Meeting #2: Early August

Our top priority is to ensure a safe and smooth experience for all students and staff. This is the first in a series of meetings, and we are committed to keeping you informed throughout this process. Updates can be found on our construction planning webpage and the Bond 2025 website.

Thank you for your continued support of Westwood Junior High and Richardson ISD.