Construction Update: Track & Field Improvements

Forest Meadow Chargers Logo

Exciting news! The District has finalized the scope of work for the Forest Meadow MS Track and Field. These upgrades will align our facilities with those at Lake Highlands Middle School.

Project Scope

  • Field: New grading, irrigation, sod, and goalposts for the playing surface.
  • Track: Removal and replacement, including new curbs, subgrade, and a rubberized surface with fresh striping.

Timeline & Logistics

  • Start Date: Mobilization begins May 18, 2026.
  • Campus Impact: The contractor is working closely with Facilities and campus leadership to ensure minimal disruption during the final week of school.
  • Completion: Targeted for August 1, 2026 (weather permitting).

We look forward to welcoming our students back to these improved athletic facilities this fall!